Feature #3081

open

Fund withdrawal – Here also we can add Tether Network and Bank Transfer options

Added by Vimesh C about 2 months ago. Updated about 2 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
Start date:
10/15/2025
Due date:
10/15/2025 (56 days late)
% Done:

100%

Estimated time:
6:00 h
Spent time:

Description

Task reported by sumitha.

Actions #1

Updated by Shiju Koshy about 2 months ago

  • Tracker changed from Bug to Feature
  • Due date changed from 10/14/2025 to 10/15/2025
  • Start date changed from 10/14/2025 to 10/15/2025
  • Estimated time set to 6:00 h
Actions #2

Updated by Shiju Koshy about 2 months ago

  • Status changed from New to In Progress
Actions #3

Updated by Shiju Koshy about 2 months ago

  • Status changed from In Progress to Resolved
Actions #4

Updated by Shiju Koshy about 2 months ago

  • % Done changed from 0 to 100